Flanders: Insufficient grid capacity for off-shore wind and large PV plants in Belgium

Last update: 2022-02-13

Let's Start
Solar power
Wind power
Hydro power
Biomass
2022-02-13
Last update on this barrier
//About

Grid regulation and infrastructure

Lack of infrastructure and infrastructure development

The biggest barrier to offshore wind is the connection to the grid:

Both the transmission as well as the distribution grids are part of regional competence. Since, only Flanders has a coastline, the expansion of the grid to accommodate new offshore wind parks falls squarely in Flemish hands. Obtaining permits takes a lot of time, due to the strong resistance to grid expansion. This is also noticeable for larger PV plants. 

The problem is that new grids must be built underground. The legal maximum threshold for total kms above-ground grid poles has been reached. Every meter built above ground must be removed elsewhere.

Elia received 5 billion EUR in 2020 from the federal government to further expand the transmission grid. However, this development will have a time horizon of 10 years. This remains the major concern point, the largest offshore issue is the 2030 timeframe, in which the capacity is planned to increase from 2GW to 4GW offshore wind. In this regard, strengthening the network is not enough, there has to be further grid development. 

For now, the grid development is realistically planned for 2028.  However, it is unclear how the capacity can increase gradually between 2020 and 2027, while no grid development has yet taken place. 

Tech //

Affected technologies

This online database provides information on barriers and best practices for wind onshore, wind offshore, PV rooftop and PV ground-mounted technologies.

Wind power

RES-E onshore wind


Severity


Spread

Wind power

RES-E offshore wind


Severity


Spread

Solar power

RES-E PV ground-mounted


Severity


Spread

Solar power

RES-E PV rooftop


Severity


Spread

Authorities//

Barrier

Competent authorities

For Flanders: Insufficient grid capacity for off-shore wind and large PV plants

Authority (Original name) Authority (English) Link
Transmission System Operators
EliaElia (TSO)Visit
Legal//

Barrier

Legal Sources

For Flanders: Insufficient grid capacity for off-shore wind and large PV plants

Source (original name) Source (english name) Link
Goedkeuring van het federaal ontwikkelingsplan 2020-2030 van het transmissienet voor elektriciteitApproval of the federal development plan 2020-2030 of the transmission grid for electricityVisit
Federaal Ontwikkelingsplan 2020 - 2030Federal Development Plan 2020-2030Visit
Besluit van de Vlaamse regering van 23 september 1997 houdende definitieve vaststelling van het Ruimtelijk Structuurplan VlaanderenDecision of the Flemish Government of 23 September 1997 regarding the definitive adoption of the Flanders Spatial Structure Plan Decision of the Flemish Government of 23 September 1997 regarding the definitive adoption ...Visit