Unpredictable and complex process for rooftop PV approval in Switzerland

Last update: 2022-06-17

Let's Start
Solar power
Wind power
Hydro power
Biomass
2022-06-17
Last update on this barrier
//About

Administrative processes

Complexity and transparency of administrative procedure

In order to install rooftop PV on a house, 4 steps with different agencies are required:

1. Approval of the municipal authority,

2. a construction approval/ notification procedure to municipal authority,

3. grid connection approval of the local grid system operator,

4. notification with ProNovo (authority for funding program).


While the length of the procedure has decreased over the past years, representatives of PV Associations claim that the approval of the local municipality is still the most unpredictable process step. It is possible that the request for the notification procedure is denied or that the municipality demands additional modifications like the order of the PV panels on the rooftop. In addition, the approval and notification procedures might differ in individual cantons from municipality to municipality. 

Representatives of the Bundesamt für Energie (Federal office of Energy) have objected to these critiques, saying that in most cases there is no approval procedure, except for historical buildings. In all other cases, a simple notification to the municipality is sufficient.   

Tech //

Affected technologies

This online database provides information on barriers and best practices for wind onshore, wind offshore, PV rooftop and PV ground-mounted technologies.

Solar power

RES-E PV rooftop


Severity


Spread

Authorities//

Barrier

Competent authorities

For Unpredictable and complex process for rooftop PV approval

Authority (Original name) Authority (English) Link
Eidgenössisches Departement für Umwelt, Verkehr, Energie und KommunikationFederal Department of the Environment, Transport, Energy and Communications