Realisation period for PV in Netherlands

Last update: 2021-10-20

Let's Start
Solar power
Wind power
Hydro power
Biomass
2021-10-20
Last update on this barrier
//About

Grid regulation and infrastructure

Duration of RES grid access

The SDE decree sets out that in order to be eligible for the SDE++ subsidy, PV projects must be realised within 2 years from the moment that the subsidy was granted. In the case that the PV project is not realised within this timeframe, the project developer will not be allowed to apply for a SDE++ subsidy for one other year. Grid operators often state that in order to reinforce the grid, they have to wait longer than 2 years. This can therefore cause issues and has made the implementation of rooftop PV projects within 2 years increasingly difficult.  

Tech //

Affected technologies

This online database provides information on barriers and best practices for wind onshore, wind offshore, PV rooftop and PV ground-mounted technologies.

Solar power

RES-E PV ground-mounted


Severity


Spread

Solar power

RES-E PV rooftop


Severity


Spread

Other Barriers?

Close